Ellesmere Port
Our client is fitting the internal heating and ventilation units to a new build large industrial warehouse. The total footprint of the building is 62,000m² yet only had a maximum eves height of 18m with sprinkler systems in the roof limiting usable height.
What we planned
We supplied a full lifting package with all required lifting equipment including a telehandler with an operator for offloading and moving loads around the warehouse. We were provided concrete slab design to work with and ensured our outrigger loadings worked with the requirements.
What we did
Over a week-long project we supplied Bocker AK46 on full contract lift with telehandler, telehandler operator, additional mats and required lifting equipment. We utilised our in house multi mat system to reduce outrigger loadings and protect the new concrete slab. All works were completed safely and within initial timescales.